The Coca Cola Fairlife Upgrade Process Piping Project involves renovating and adding new building utility piping systems to serve a new 13,000 sqft production space that will increase Fairlife’s production capacity significantly for their whole line of milk drinks and milk-based protein drinks in their current 145,000 sqft Peterborough, ON facility.

Mechanical Systems

Kelson is installing a whole new 10” high pressure steam and high pressure condensate distribution system and 6” process water system that runs over 400 feet along new rooftop supports from the existing incoming water room and boiler plant, to the new production space on the other side of the Fairlife facility. High pressure steam, condensate, domestic water, compressed air, process water, acid and alkaline systems are all being installed in the new production space, feeding from existing tie-ins completed during planned plant shutdown periods.