Kelson was mechanical contractor for the Michael Garron Hospital ICU renovation project. This involved installing new sinks, macerators, dialysis boxes, and pressure monitors into existing patient rooms on the second floor of Michael Garron ICU. Multiple point-of-use (POU) water heaters were also installed due to the lack of hot water availability from the base plant to ensure hot water delivery within seconds at faucets.

Mechanical Systems

Kelson Mechanical Highlights: Kelson tied in new fixtures to existing services utilizing pipe freezing to accomplish this with no hospital shut downs. Installing glass drainage piping for the corrosive waster expelled out of the dialysis boxes. This was an occupied facility with strict health and safety procedures in place. After hours work was completed to have minimal impact on hospital operations.