Demolishing an existing 15 ton AC Unit in the Sick Kids data centre and replacing it with a new 30 ton AC unit. While the existing unit is shutdown we are operating two 5 ton temporary cooling units to handle the load.

Mechanical Systems

Kelson mechanical highlights: Prime hospital job with IPAC requirements and a very tight work space.