Royal Bank of Canada Office Renovation - 330 Front St., Toronto
Completion: August 27, 2015
Location: Toronto
Size: 142,000 square feet
Kelson was the Mechanical Contractor for the office renovation for RBC at 330/310 Front Street. This project consisted of the removal of all existing plumbing and HVAC lines back to their mains. Â Once removed, new lines were installed for connection to small kitchenette on each floor and a washroom on two floors. HVAC work consisted of new branch lines to be built off the existing main supply duct ring. Â This was an occupied facility. This was a fast-paced project with a quick turnaround time due to owner requirements.
Mechanical Systems
330 Front
Work on levels 2-11 and roof, minimal work on level 3 and 10
Cut/cap/make-safe
Demo by others
Existing main supply ductwork to remain, CTE with small duct to new diffusers. Ceiling is a return air plenum
CTE plumbing and run new lines for fixtures
No heating/chilled lines
New refrigeration lines for new small DX splits
310 Front
Work on levels 2, 3, and roof
Same scope as 330 except no plumbing fixtures