Projects
Mars Pegasus Canada Inc. Manufacturing Plant (Chocolate)
Completion: November 01, 2016
Location: Newmarket
Size: 40,000
This project was an addition to an existing Mars Chocolate facility where Kelson installed the new underground piping as well as the following new equipment which mad up an upper and lower mechanical room: Â Â Â
3 - AHU’s on the roof
1 – Cooling Tower
1 – Chiller
14 – Armstrong Drive Mounted Pumps
2 – Heat exchangers
3 - Storage Tanks                                                      Â
Project Highlights
This project had a very tight schedule as well we had to adhere to the clean design spec which had us modify the majority of our installation and skid designs.