245 Eglinton Mechanical Equipment (HVAC Replacement) - PRIME
Completion: April 11, 2018
Location: Toronto
Renovation of mechanical systems in 4 story office building. Job contains 7 rooftop units, 3 boilers, 1 cooling tower, 10 pumps, remove and replace 166 VAVβs and 89 control valves in the perimeter heating loop. Upgrade of all electrical services feeding new equipment.
Mechanical Systems
Kelson mechanical highlights:
HVAC Equipment Removal: Kelson was responsible for removing seven rooftop air handling units, three boilers and a cooling tower. Additionally, Kelson was responsible for the removal of smaller pieces of equipment, including ten pumps, 166 variable air volume (VAV) boxes, and 89 controls valves.
HVAC Equipment Supply: Kelson managed the procurement process, tendering the equipment, negotiating purchase agreements and managing the shop drawing process.
HVAC Installation: Kelson was responsible for coordinating and installing all pieces of equipment, and associated piping. Rooftop units, boilers, and cooling tower installation required multiple crane lifts.