Kelson was the Prime Contractor for the Westin Harbour Hotel Chiller Upgrade as an improvement to the HVAC system. Removing existing 800 ton chiller and replacing with a 500 ton and 300 ton chillers. New accessory equipment was 6 – 6” pumps, side stream filtration unit, power distribution panels with transformers and VFD’s. This project had very tight timeless and Kelson achieve scheduled dates.

Mechanical Systems

Mechanical Highlight: New chillers to run on continual system for energy conservation.

HVAC Equipment Removal: Kelson was responsible for the safe decommissioning, refrigerant removal, demolition of existing equipment and safe disposal of the existing chiller plant.

HVAC Equipment Supply: Kelson managed the procurement process, tendering the equipment, negotiating purchase agreements and managing the shop drawing process. 

HVAC Installation:   The chiller installation required complex rigging and hoisting into the building up the parking garage ramp. Installation and commissioning of the chiller complete with associated pumps and VFDs. Â