1 Disconnect existing old 750-ton chiller (disposed by others).

.2 Connect/insulate new chiller to existing chilled water and condenser water systems.

.3 Provision of new outsider air louver.

.4 Provision of new outside air damper.

.5 Provision of mechanical components related to chilled water plant controls.

.6 Installing the chiller isolation butterfly valves supplied by the Controls contractor.

.7 Testing, Adjusting and Balancing.